Vogtle gets clean bill in NRC environmental review
The NRC has issued a finding that there are no environmental impacts that stand in the way of licensing two new reactors at Southern’s Vogtle site.
The draft Supplemental Environmental Impact Statement will be discussed during a public meeting Oct 6 in at Augusta Technical College's Waynesboro campus. Site work is under way, and company officials have said they expect the license to be issued in late 2011.
Southern Nuclear has applied for a combined operating license to build and operate two Westinghouse AP1000 1,1150 MW reactors that would go online in 2016 and 2017 at a cost of about $14.5 billion.
Southern is the only new reactor project to receive federal loan guarantees. The Department of Energy program has been mired in bureaucratic delays at and foot dragging by Congress over expansion of the program.
The Georgia Public Utility Commission has authorized the utility to charge rate payers for the cost of the plant while it is being built. This move will save rate payers over a billion in financing costs. [ See this profile in Forbes for Sept 9 for more insights. ]
Environmental groups will try to raise new issues regarding the reactor designs saying that they are subject to corrosion. The Atomic Safety and Licensing Board has scheduled a meeting Sept 17 to hear from the Blue Ridge Environmental League.
First components arrive at Vogtle
The first components of Vogtle's new nuclear reactors arrived in Georgia this week after a 10,000-mile journey from Japan.
"These parts are being shipped to the port of Savannah -- spending four weeks at sea," said David Jones, Southern Nuclear's site vice president for Plant Vogtle Units 3 and 4.
The parts, which began arriving by flatbed truck last week, include 58 massive steel plates. The plates will form the bottom of Unit 3's containment vessel.
Exelon says low gas prices could postpone the nuclear renaissance for two decades
Chicago-based Exelon CEO John Rowe (right) has never been one to pull his punches, and this week was no exception. Rowe said in an interview with the Bloomberg financial wire service in New York that low prices for natural gas are likely to continue for a long time. The effect will be pushing back the construction of new U.S. nuclear power plants by a "decade, maybe two."
According to wire service reports, Rowe said that the price of natural gas would have to rise to $8 per million BTU and carbon taxes would have to rise to $25/ton to make the power prices from new merchant nuclear reactors competitive with gas-fueled plants.
If there is no carbon tax, gas would have to rise to $9 or $9.50 to make the reactors economically attractive, Rowe said. Natural gas prices have fallen 33 percent this year and are down 76 percent from the 2005 high of $15.378.
Exelon has essentially mothballed its planned twin reactor project in Victoria County, Texas. It scrapped its license application with the NRC and turned in an Early Site Permit which preserves its options for 10-20 years.
For anyone who follows Rowe’s pugnacious prognostications, this isn’t news. He said “it isn’t a renaissance yet” in a February 2010 interview with Bloomberg following President Obama’s award of an $8 billion loan guarantee to Southern for the twin-reactor Vogtle site.
Exelon has aggressive power uprate plans underway that could generate between 1,300 and 1,500 MW of additional generation from existing nuclear plants within 8 years without any new construction at about half the cost of building a new nuclear power plant.
Exelon manages the nation’s largest fleet of nuclear reactors with 17 of them at 10 sites in Illinois, Pennsylvania, and New Jersey.
Davis-Besse to flip its lid in 2011
First Energy’s Davis-Besse 879 MW plant located near Toledo, OH, will replace its reactor lid in 2011 instead of 2014. The utility said at an NRC meeting held last week that it will move up the date for the 15-month shut down to October 2011.
The decision follows the completion of a six-month long special inspection by the NRC of cracks in parts replaced just six years ago.
Also, First Energy has submitted an application to the NRC to extend its license for another 20 years. The current license expires in 2017. The reactor came online in 1977.
The plant has a checkered past which it has sought to overcome with a renewed emphasis on safety. NRC Manager Mark Satorius, told the Cleveland Plain Dealer Sept 11 the six month review that just ended at Davis-Besse “probably constitutes one of the most thorough inspections” he’s ever worked on.
First Energy said it made a decision, “based on safety” to set aside its plan to change out the reactor vessel lid in 2014 and move the project up to 2011. Davis-Besse VP Barry Allen told the Plain Dealer the decision to do so “was not made lightly” because of the work that will need to be done to meet the earlier date.
License renewal for Seabrook draws opposition
New England loves cheap electricity when it can get it from nuclear reactors because it pays so much for fossil fuel. That hasn’t stopped a coalition of local and national anti-nuclear groups from seeking to pitchfork an early license renewal for the 1,245 MW Seabrook nuclear power station.
The plant started operations in 1990 and has applied to extend its license, which expires in 2030, to run until 2050.
Opponents say they want the application to be set aside until 2020, or ten years prior to renewal. They say the application is “premature” given the unknowns of plant maintenance, safety, reliability, technology, and future power needs.
The plant has an outstanding safety and operating record which makes the opposition by the anti-nuclear groups more of a knee-jerk reflex than one based on reality.
Salem containment cracks and leaks draw attention
The NRC has ordered New Jersey-based PSEG to answer questions about cracks in the exterior containment walls of the Salem, NJ, reactors. The agency is concerned that numerous cracks were not identified due to a 10-year cycle of inspections rather than one every five years.
(Image: steel reinforcement bars at the Salem 1 nuclear reactor via Energy Matters blog.)
The NRC also found evidence of multiple unreported leaks and corrosion.
Environmental groups pounced on the NRC’s review. They said the issue, which came up during a review of the twin Salem, NJ, reactors license renewal application, should be treated as violations. But Neil Sheehan, an NRC spokesman, told wire services safety was never an issue. He acknowledged there “are some flaws in the containment structure.”
The NRC review turned up corrosion and leaks that had not previously been publically disclosed. This incensed the ’Unplug Salem’ environmental group which called the reported leaks “negligence.”
Roger Witherspoon, a New Jersey-based journalist, has a detailed report on the problems at the Salem plant.
Joe Delamr, a PSEG spokesman, said the utility is addressing the NRC’s concerns.
PSEG is also in the planning stages to build one or two new reactors at the site. No decision has been made, but the utility filed for an Early Site Permit last May.
# # #